STAGES OF PLAN PRODUCTION
|
Stage |
Steps (to be caried out sequentially) |
Timeframe |
|
“Get Ready” Before the 30-month process starts |
Prepare and publish Local Plan Timetable |
Before notice |
|
Give notice of commencement of plan-making process – at least 4 months’ notice must be given |
Publish alongside LP Timetable |
|
|
‘Scoping’ consultation – engagement, plan content, vision and required evidence |
No minimum period |
|
|
Pass through Gateway 1 (Readiness Check) – focus on scope, strategic priorities, project management and governance arrangements |
Before 30th April 2027 |
|
|
“Prepare the Plan” Months 1 to 23 |
Publish summary of ‘Scoping’ consultation |
|
|
‘Proposed Content and Evidence’ consultation – vision, aims and objectives, spatial strategy, evidence summary, policies + allocations optional |
6-week minimum |
|
|
Publish summary of “Proposed Content and Evidence” consultation |
|
|
|
Pass through Gateway 2 (Progress Review) - checking progress with the planning inspectorate, providing feedback on potential soundness issues |
4-6 weeks |
|
|
‘Proposed Local Plan’ consultation – version the Council intends to submit – consult combined authority (Spatial Development Strategy alignment) |
8-week minimum |
|
|
Publish summary of “Proposed Plan” consultation |
|
|
|
Pass through Gateway 3 (Final Validation) – stop / go check before examination to confirm the plan meets legal and procedural requirements |
4-6 weeks |
|
|
“Examination” Months 24 to 29 |
Submit the Plan for Examination |
|
|
Take part in the Examination – modify plan if needed (mods will extend 30-month timeline) |
|
|
|
“Adoption” Month 30 |
Get full Council approval to adopt plan |
|
|
Publish the Plan and the adoption statement |
|